Gravells Kia Roll Out - Bridgend
Our second Kia site complete. Located in Bridgend, we completed the installation of 11 EV Baes with 1 being a B600 for the DC Charger. We trench 24m through slabs 55m through gravel and 6m through asphalt. We laid a total of 185m of ducting (63mm, 110mm and 150mm). We also installed 3 x 600mm Access Chambers. This site is now ready for the chargers to be fitted to all bases.
​
​